July 09 2024

Project Approved by Town Council

The project was approved at the July 9, 2024 Town Council Meeting. 

Read the agenda

September 16 2024

Project Start Date

The project began on September 16, 2024. 

October 16 2024

Right Lane Closure

Starting Wednesday, October 16 the right turn lane on Evergreen Road (southbound) will be closed for construction through Wednesday, October 23.

Evergreen Road will be ONE-LANE to the south during this period.

This is 24 hour/day closure will affect school traffic in the morning and the afternoon. Parents can choose to use Little Beaver Trail during this time.

During the days before 10/16 and after 10/23, the Town may need to also temporarily close the right turn lane from time to time during the day between 9am-3pm.

November 28 2024

Projected End Date

The project is projected to end around Thanksgiving.